Concorde Way, Woodley

07 May — 14 May

Delays unlikely – Give & take traffic control

Works location: Junction with Viscount Way

Works description: Approximately 6m roadcrossing at junction with Viscount Way

Responsibility for works: Scottish and Southern Power Distribution

 

 

Viscount Way, Woodley

07 May — 17 May

Delays unlikely – Give & take traffic control

Works location: Junction of Gemini Road to Miles Way

Works description: Excavate approximately 90m in footway with one roadcrossing to connect, four streetlights and disconnect two streetlights

Responsibility for works: Scottish and Southern Power Distribution

 

Colemansmoor Road, Woodley

08 May — 10 May

Delays possible – Some carriageway incursion

Works location: 102 Colemansmoor Road

Works description: B Box Exchange <33mm Fway in Footway.

Responsibility for works: Thames Water

 

Comet Way, Woodley

08 May — 10 May

Delays possible – Some carriageway incursion

Works location: 45 Comet Way

Works description: Audit of Contractors Work in Footway.

Responsibility for works: Thames Water

 

Howth Drive, Woodley

08 May — 10 May

Delays possible – Some carriageway incursion

Works location: 59

Works description: Serv Pipe Relay Inc Fitting Sz P Fway in Footway.

Responsibility for works: Thames Water

 

Anderson Avenue, Earley

08 May — 10 May

Delays unlikely – Some carriageway incursion

Works location: 65

Works description: B Box Exchange <33mm Fway in Footway.

Responsibility for works: Thames Water

 

Burns Close, Woodley

08 May — 10 May

Delays unlikely – Some carriageway incursion

Works location: 7 Burns Close

Works description: Service Pipe Repair <33mm Fway in Footway.

Responsibility for works: Thames Water

 

Warren Road, Woodley

08 May — 09 May

Delays unlikely – Some carriageway incursion

Works location: 14

Works description: Rectify Dangerous rein defect – non-pay in Footway. Our intention is to complete the Permanent Reinstatement in the same phase

Responsibility for works: Thames Water

 

B3350 Pitts Lane, Earley

08 May — 10 May

Delays likely – Traffic control (Stop/Go boards)

Works location: From junction with Town Lane to junction off Old London Road (A4 Service Road) near kwikfit.

Works description: To re-lay anti-skid along approximately 50m of trench

Responsibility for works: Scottish and Southern Power Distribution

 

Loddon Bridge Road, Woodley

09 May — 10 May

Delays likely – Traffic control (two-way signals)

Works location: Opposite 196

Works description: Replace 1 jointbox, replace frame and cover(s) (915mm x 445mm) in Footway

Responsibility for works: Openreach

 

Drovers Way, Woodley

09 May — 13 May

Delays possible – Some carriageway incursion

Works location: 54 Drovers Way

Works description: Service Pipe Repair <33mm Fway in Footway.

Responsibility for works: Thames Water

 

Church Road, Woodley

10 May — 14 May

Delays possible – Traffic control (give & take)

Works location: Opposite 28-30

Works description: to excavate to transfer lv mains service to replacement column – off peak hours and off road parking where possible

Responsibility for works: Wokingham Borough Council

 

B3350 Church Road, Earley

13 May — 13 May

Delays likely Traffic control – (Stop/Go boards)

Works location: 70-72

Works description: Planned cover replacement — works intended to include first time permanent reinstatement in the same phase

Responsibility for works: Thames Water

 

Woodlands Avenue, Woodley

13 May — 15 May

Delays possible – Some carriageway incursion

Works location: 37 metres from Fairwater Drive

Works description: Build 1 precast chamber in 915mm x 445mm x 965mm deep in Footway,Install 5m of 1 way poly duct in Footway

Responsibility for works: Openreach