Search

Weekly scheduled roadworks – 12 November

Woodley roadworks

For more information about each instance of roadworks, please click the link in the road name or contact the responsible organisation.

 

B3350 Church Road, Earley, Wokingham

14 November — 14 November

Delays likely – Road closure

Works location: 70-72 

Works description: S81 PLANNED COVER REPLACEMENT–WORKS INTENDED TO INCLUDE FIRST TIME PERMANENT REINSTATEMENT WITHIN SAME PHASE

Responsibility for works: THAMES WATER

 

Crockhamwell Road, Woodley, Wokingham

17 November — 20 November

Delays possible – Some carriageway incursion

Works location: WAITROSE, 108, CROCKHAMWELL ROAD, WOODLEY, READING, RG5 3JH

Works description: B Box Repair <33mm Fway in Footway 

Responsibility for works: THAMES WATER

 

Culver Lane, Earley, Wokingham

14 November — 18 November

Delays possible – Traffic control (give & take)

Works location: OS 26 CULVER LANE

Works description: SECT81 TO REPAIR THE CW BOX

Responsibility for works: CITYFIBRE METRO NETWORKS LTD

 

Fairwater Drive, Woodley, Wokingham

12 November — 14 November

Delays possible – Some carriageway incursion

Works location: 135

Works description: Sluice Valve Box replace Fway in Footway.

Responsibility for works: THAMES WATER

 

Milton Road, Earley, Wokingham

12 November — 14 November 

Delays possible – Some carriageway incursion

Works location: 14

Works description: Boundary Box Resite Fway in Footway.

Responsibility for works: THAMES WATER

 

Carrick Gardens, Woodley, Wokingham

12 November — 14 November

Delays unlikely – Some carriageway incursion 

Works location: 35

Works description: B Box Exchange <33mm Fway in Footway.

Responsibility for works: THAMES WATER

 

Duncan Road, Woodley, Wokingham

12 November — 18 November

Delays unlikely – Some carriageway incursion

Works location: O/S NEW BUILD NO 29

Works description: SGN TO LAY NEW SERVICE FROM N/S C/W TO CONTINUE FURTHER INTO THE PRIVATE.

Responsibility for works: SGN

 

Footpath in Front of 74 to 90 Kingfisher Drive, Woodley, Wokingham

12 November — 14 November 

Delays unlikely – Some carriageway incursion 

Works location: O/S 100,,100,KINGFISHER DRIVE ,WOOD, LEY ,BERKSHIRE ,RG53LG, , , 

Works description: HAND DIGGING ONLY TO EXPOSE EXISTING TELECOMS INFRASTRUCTURE TO PROVIDE NEW SERVICE TO NEW CUSTOMER.

Responsibility for works: Openreach

 

Kingfisher Drive, Woodley, Wokingham

12 November — 25 November

Delays unlikely – Traffic control (give & take)

Works location: 62-72 

Works description: Iron works around the gulleys. This is rolling roadworks that will be going down through the road, for more information about which sections will e worked on at which times, please contact Wokingham Borough Council.

Responsibility for works: Wokingham Borough Council

 

Old Bath Road, Woodley, Wokingham

19 November — 25 November 

Delays unlikely – Traffic control (give & take)

Works location: O/S NO 25

Works description: SGN TO INCREASE CAPACITY IN THE F/S C/W.

Responsibility for works: SGN

 

Rivermead Road, Woodley, Wokingham

13 November — 15 November

Delays unlikely – Some carriageway incursion 

Works location: O/S 42 RIVERMEAD ROAD, WOODLEY, READING

Works description: LAY 9M DUCT IN FOOTWAY & SWEPT TEE

Responsibility for works: VIRGIN MEDIA

Update from Wokingham Borough Council 07/11/19.

The following road closures will be in place:

“Tennyson Road, Woodley between its junctions with Keats Road and Oban Gardens.

The alternative route for all vehicles affected by this restriction shall be via Keats Road and Clivedale Road, or by this route in reverse. 

Works requiring this restriction will take place between 25th November and 27th November 2019

The reason for these prohibitions is to allow Thames Water contractors to undertake service pipe relay work in safety.”

Share the Post: