Thousands of residents have improved roads outside their homes after Wokingham Borough Council completed resurfacing on almost 100 streets across the area. The council took advantage of quieter roads in April and May to complete work on key travel routes across the borough when many were not using their cars.
Works have continued through the spring and into the summer, with more than £2million spent to improve surfaces in all areas of the borough. More investment in improving the borough’s roads will take place in September, with more full resurfacing schemes planned to take place through the autumn. More information on these will be made available later this summer, with residents on the roads the council will be working on informed directly by letter.
The works included 21 roads, which were carried over from our 2019-20 programme, which was delayed by wet weather.
Treatment type
Completed
Cost (approx.)
Full resurfacing
17
£1,142,553
Surface dressing
19
£754,058
Micro-asphalt
63
£208,057
TOTAL
99
£2,104,694
More information on the different types of roads treatment can be found on the council’s website.
“We’ve earmarked £8million for road improvements across the borough in 2020-21 and it’s fantastic many residents will already be seeing the benefits of this,” said Cllr Pauline Jorgensen, executive member for highways and transport. “We know our residents want to see investment in our roads and with more than half the completed roads so far being residential, that means many will see it outside their own front doors, as well as on key transport routes.
“We’d like to thank our contractors and partners on this project, for helping us bring it forward quickly and take advantage of quieter roads to complete these improvements with minimal disruption to residents.”
Lockdown measures caused road usage in the borough to drop by 50 per cent and roadworks by utilities companies to drop by more than 33 per cent, providing an opportunity to complete work in potentially disruptive locations first including the A4 and the Showcase roundabout.
The roads were chosen through scoring from surveys on roads across the area, meaning the council spends money on roads where work is most needed. Work often takes place in off-peak hours during the day, 9.30am to 4pm, or overnight to minimise disruption to residents.
This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.
Strictly Necessary Cookies
Strictly Necessary Cookie should be enabled at all times so that we can save your preferences for cookie settings.
If you disable this cookie, we will not be able to save your preferences. This means that every time you visit this website you will need to enable or disable cookies again.